Big things are underway at The Queen Elizabeth Hospital site in South Australia with the construction of the central atrium pile cap.

Dodging recent inclement weather, including rain and hail, our team recently installed 100 tonnes of reinforcing in four days and successfully completed an early morning concrete pour.

The first concrete truck arrived on site at 2.00am and by 8.30am 800m3 of concrete had been poured. This fantastic achievement builds on what has been a tremendous start by the team and sets a solid foundation for things to come!