Pharmaceutical Manufacturing Facility
Location:
Broadmeadows, Victoria
Contract:
ECI / Construction Management
Customer:
CSL Behring
Duration:
29 months
Upgrading a world-leading pharmaceutical facility in a 24/7 live environment
This project was delivered in three phases – preconstruction, early works and main works – across nearly 3,000 m² within an operational pharmaceutical manufacturing facility in Broadmeadows.
The completed scope included new GMP change amenities on Level 3, installation of specialised clean water and gas systems, a bulk process system incorporating Clean-in-Place (CIP) and temperature control skids, and the integration of new fill-finish equipment, including a new aseptic filling line.
The program commenced with a successful Early Contractor Involvement (ECI) phase, where Built Environs provided cost planning, program development, design and buildability advice, and detailed site logistics planning.
Working within a live brownfield environment required careful planning to protect critical operations. Multiple work zones were established and coordinated with the client to minimise disruption, with key tie-ins, commissioning and high-impact activities scheduled around four major shutdown periods. This required detailed programming to support continuous 24/7 operations over several weeks.
Shutdown works included complex craning and rigging of structural steel, process vessels and fill-finish equipment through temporary roof and wall access openings. Cleanroom delivery incorporated Askin panel wall and ceiling systems and durable multi-layer epoxy flooring, with mechanical, fire, electrical, clean utilities, process waste and control systems installed while operations continued. Final tie-ins, commissioning and validation were completed during the planned shutdown windows.
Fast Facts:
- The project spans nearly 3,000m2 within a 24/7 operational pharmaceutical manufacturing facility
- Key works include new GMP change amenities, specialised clean water and gas systems, and a bulk process system with Clean-in-Place (CIP) and temperature control skids
- Due to the facility’s operational nature, brownfield zones were planned to minimise disruptions, with shutdown periods scheduled for key activities and commissioning tasks

Creative Construction
Innovative rigging solutions for structural steel installation in a continuous operational environment
Construction within a 24/7 operational environment presented unique challenges, especially when installing crucial structural steel elements to form the primary platform for the new Level 3 change and gowning rooms supporting the manufacturing area. The structural platform required innovative rigging methodologies to ensure uninterrupted operations and a safe, manageable installation process. This included modifying the design of the structural steel components, such as splicing and connection details.
A specialised rigging access hatch was installed in the roof to facilitate the delivery of the main steel elements into the workspace. Once on-site, the elements were expertly manoeuvred using dollies and a manual conveyor system before being securely positioned with chain blocks.