Customer: Department of Defence Construction period: 11 months Contract type: Construct only Project Capabilities![]() ![]() |
Fast Facts
|
Built Environs completed additional work for the Department of Defence at RAAF Base Pearce at Bullsbrook, WA.
Our scope of work included construction of a single-storey building; demolition of eleven redundant base facilities; and upgrading of 12 km of base perimeter fencing. Unique to the project was the supply and installation of a new grey water treatment plant for landscape irrigation.
A particular challenge was working within an operational RAAF base with security and airside access restrictions. Throughout the project, the Built Environs team was committed to the active management of both communications and construction works so that base operations continued uninterrupted. The base remained fully operational throughout construction due to advanced planning and coordination of construction activities with base users and stakeholders.